Here is the very latest chronology for the long awaited project to improve the intersection of Mobile Highway and Beulah road, including the addition of a stoplight. This project is moving forward, here is the latest information direct from FDOT:
Letting: 12/14/2017
Anticipated Award: 01/08/2018
Anticipated Execution: 01/30/2018*
Anticipated NTP: 2/27/2018
This Contract has 210 Contract Days (plus holidays,
weather, added work, etc.).
This Contract also has 30 days for acquisition time
for signal equipment.
Bid Amount $1,508,857.51
No comments:
Post a Comment
Abusive, profane, and/or off-topic posts will not be allowed. Unprovoked ad-hominem attacks will not be tolerated. All posts are subject to moderation, posts that violate these policies, spam, posts containing off-color language, and any other inappropriate comments or content, as determined by the blog administrator, will remain in moderation and may not be added on the site. This site is not my campaign site, but in an abundance of caution I will offer the below disclaimer.