A Pedestrian Overpass project has been imagined for the Beulah area---if state funding could be acquired to construct it. Initial estimate is high at $3 Million |
"Commissioner
Bergosh-
Received
the attached estimate for the most recent pedestrian bridge completed by FDOT
in Panhandle (Panama City). This bridge was bid last year from my
understanding, therefore, we should estimate the following factors:
Estimated
cost of Bridge:
$3.1 M
Year
2022 Cost Increases (30%):
$0.93M
Programmed
project in 5th year inflation
(30%):
$0.93M
$5.0M
This
cost includes the design, construction, and construction inspection
services. This is just an estimated cost not to include any right-of-way
acquisition if needed."
No comments:
Post a Comment
Abusive, profane, and/or off-topic posts will not be allowed. Unprovoked ad-hominem attacks will not be tolerated. All posts are subject to moderation, posts that violate these policies, spam, posts containing off-color language, and any other inappropriate comments or content, as determined by the blog administrator, will remain in moderation and may not be added on the site. This site is not my campaign site, but in an abundance of caution I will offer the below disclaimer.