I have established this blog as a means of transparency to the public, outreach to the community, and information dissemination to all who choose to look. Feedback is welcome, but because public participation is equally encouraged, appropriate language and decorum is mandatory.
Showing posts with label develpment. Show all posts
Showing posts with label develpment. Show all posts

Friday, September 23, 2022

Approving Developments--Inside the Process Part III: Environmental Permits Granted

5th Dimension's Rendering of this proposed development


As I mentioned in parts I and II of this series of posts about a multi-family development in the Perdido area of District 1--there were residents that were caught off guard by this project.

Several came to a meeting last month, one asked for a townhall, which I have now subsequently scheduled.

Look, I'm concerned about traffic, too.  I understand the issues and have heard from many constituents that live in this area about traffic congestion.  And I am working that issue to the extent I am able and within the confines of the revenue available.  And there are a lot of great projects in the works and in the planning stages right now for that area.

This said, I am not an agent, cheerleader, or spokesman for this development, this  developer, or his representatives. I am a county commissioner for this district and because folks are concerned I have assured them that I will leave no stone unturned in ensuring that every "i" was dotted and "t" was crossed as it pertains to this particular development having been approved properly.  I have asked for and received a raft of information that the staff looked at and used upon which they based their approval decision.  I have also asked staff to have the developer's representative at the town hall as well as the traffic study's author.  We will see if they show up.  I believe it would be in their interest to do so.

Thus far, it appears to me that everything has been done in accordance with state and local ordinances and the County's land development code.

As I said I would do, I am going to link all documents related to this development here on this blog so citizens can see the same information I am seeing in the lead up to the town hall on the 25th of next month..

This morning I am linking a very important permit that was received, the Northwest Florida Water Management District approval.  Lots of additional supporting documents for this project and this particular permit can be found by clicking this link and searching under the developer name in the search field, JH Capital, LLC.  Readers will at this site see all the charts, maps, and additional

Wednesday, September 21, 2022

Approving Developments--Inside the Process, Part II: A Traffic Engineer Reviews the Traffic Analysis

5th Dimension's Rendering of this proposed development

 In part one of this series we discussed how the process to approve a 325 unit development at the foot of the Baars Bridge in Perdido occurred.  The particular focus of the first blogpost was on the traffic impacts of this project and also, importantly, the timeline of this development (this approval was well underway as were the lion's share of all necessary environmental permits, before this was in D1; It had been an in the works project--being planned and envisioned for years in D2 ---and would have happened regardless of whether this parcel remained in D2 or went to D1 after the redistricting).  That's #1. 

#2 is the Traffic impacts.  To drill down on these particular concerns,  I linked the traffic study in that post.  I also asked our current Traffic Engineer to review the study and provide feedback (he was not employed with the county when this was submitted and the development order was approved by the county--and unlike some of the folks who commented on this topic on part one of the post--Mr. Phillips is a Professional Engineer and an expert on traffic management).

His comments and findings based on his review of the traffic study are below:

"I have reviewed the traffic analysis submitted by Dantin Consulting (Oct. 2021) for the proposed development between Canal Drive and Monterey Avenue.  The calculations all follow industry standards.  There was a concern voiced regarding the Level of Service (LOS) shown in one of the exhibits.  These calculations were performed to show none of the corridors went to a level beyond a D.  Several of the sections still meet a LOS C with one being a B.  It is important to know these calculations are NOT required for development in Escambia County of the State of Florida as transportation concurrency has been removed from State criteria quite some time ago.

Only two instances are present where a regulation was not met to the letter due to geometric constraints versus perceived benefit.  These are explained in number 5 and 6 below.

  1. Trip calculation was performed utilizing proper Institute of Transportation Engineers (ITE) land use codes and entering/exiting numbers.  These consider the development size, general location, and sample size of the data to closely mimic reality.   The PM peak hour (utilized throughout) for trip generation is greater than the AM peak.  The PM Peak Hour calculation shows 129 vehicles per hour (vph) with 79 entering and 50 exiting during that time, again in accordance with ITE data.  Ten percent of trips was dedicated to bike/ped uses.  The projected trips show that not all residents of the 325 dwelling units will leave or arrive during a one-hour period.
  2. The trip distribution to the two access points is acceptable with 60%/40% exiting at Canal/Monterey and 70%/30% entering Canal/Monterey
  3. FDOT counts from 2020 were used for background traffic on Sorrento, Gulf Beach, and Innerarity.  New counts were taken for Canal and Monterey to record background and turning movements that are occurring presently.
  4. The roadway LOS was calculated utilizing the FDOT Peak Hour Directional Volume chart for various types of roadway.  The rationale for the calculation utilizes the FDOT count station data, conversion from Annual Average Daily Traffic to Peak Hour Directional, then compare to a Level of Service on the chart.  The engineer chose level of service D to show that even at LOS D, there is capacity remaining after adding the trips from this development to the roadway segment.  Many of the segments have capacity at a LOS C as well with one segment operating at LOS B.
  5. County Design Standards Manual requires LT and/or RT turnlane if the turning movement into the site from the adjacent county road is 30 vph or greater.  The Monterey access did not warrant