Here is the very latest chronology for the long awaited project to improve the intersection of Mobile Highway and Beulah road, including the addition of a stoplight. This project is moving forward, here is the latest information direct from FDOT:
Letting: 12/14/2017
Anticipated Award: 01/08/2018
Anticipated Execution: 01/30/2018*
Anticipated NTP: 2/27/2018
This Contract has 210 Contract Days (plus holidays,
weather, added work, etc.).
This Contract also has 30 days for acquisition time
for signal equipment.
Bid Amount $1,508,857.51