"Utility companies have been notified to schedule their relocation work at the proposed foundation location. There are three underground communication lines to be relocated / adjusted to accommodate the 60” concrete drilled shaft. To date we have heard no response from the underground utilities on when their work will begin. In January 2023, the contractor estimated up to 20 weeks to have the mast-arm and cabinet delivered to the project. Which could potentially be sometime early June 2023.Based on the above, I am estimating the foundation to be installed approximately mid to late April, and the signal installation / operation to be sometime mid to late June."
Guidelines
I have established this blog as a means of transparency to the public, outreach to the community, and information dissemination to all who choose to look. Feedback is welcome, but because public participation is equally encouraged, appropriate language and decorum is mandatory.
Monday, March 20, 2023
Sorrento Road at Doug Ford Drive: Latest on the Signal Installation
Subscribe to:
Post Comments (Atom)
1 comment:
I’m hearing a rumor that this installation of a light at PBCC was canceled. Can you confirm that it’s still on the schedule to be completed and if so, when? Thanks!
Post a Comment