Guidelines

I am one member of a five person board. The opinions I express on this forum are mine only, and do not necessarily reflect the views or opinions of the Escambia County Staff, Administrators, Employees, or anyone else associated with Escambia County Florida. I am interested in establishing this blog as a means of additional transparency to the public, outreach to the community, and information dissemination to all who choose to look. Feedback is welcome, but because public participation is equally encouraged, appropriate language and decorum is mandatory. Although this is not my campaign site for re-election--sometimes campaign related information will be discussed, therefore in an abundance of caution I add the following : Political Advertisement Paid for and Approved by Jeff Bergosh, Republican, for Escambia County Commissioner District 1








Wednesday, October 13, 2021

Very Preliminary Cost Estimate for Beulah Pedestrian Bridge Comes in at $3 Million

A Pedestrian Overpass project has been imagined for the Beulah area---if state funding could be acquired to construct it.  Initial estimate is high at $3 Million


As has been discussed previously on this blog and in the press, there is an effort underway to acquire the funding necessary to construct a pedestrian overpass over 9-Mile Road in Beulah.

State Representative Michelle Salzman has indicated she will seek state funding in the upcoming legislative session for construction of this bridge in District 1.

This effort is supported by Salzman, myself, and District 1 School Board Member Kevin Adams.

If the funding is acquired and this can be built--it will be a tremendous safety enhancement for the students who attend Beulah Middle School (South side of 9-Mile Road) and live north of 9-Mile road.

It will also compliment an aggressive sidewalk construction program I will be initiating over the next 36 months to enhance the walkability and safety of the growing Beulah community.

I requested a "placeholder" estimate from our traffic and engineering departments and have now received a very preliminary estimate of $3 Million Dollars--broken down as follows in the email received:

"Commissioner Bergosh-

Received the attached estimate for the most recent pedestrian bridge completed by FDOT in Panhandle (Panama City).  This bridge was bid last year from my understanding, therefore, we should estimate the following factors:

 

Estimated cost of Bridge:                                                 $3.1 M

Year 2022 Cost Increases (30%):                                    $0.93M

Programmed project in 5th year inflation (30%):                $0.93M

                                                                                                $5.0M

 

This cost includes the design, construction, and construction inspection services.  This is just an estimated cost not to include any right-of-way acquisition if needed." 


No comments:

Political Advertisement Paid For and Approved by Jeff Bergosh, Republican for Escambia Commission D1