But we're finally on the brink of moving this project forward.
Property has been acquired (took 3 years), design funded, and construction is funded. Now, all that is left is getting this project out to bid. According to staff, we are looking at a May groundbreaking. Below is the
tentative schedule for this project based on Building Inspections being able to
review and comment on the plans within 30 days and Purchasing having out for
bids within 14 days.
- DRC Review Completed and
submitted to Building Inspections for their review
- Jan 19, 2022
- Building Inspections
review completed
- Feb 18, 2022
- Submit to Purchasing
- Feb 21, 2022
- Purchasing advertise
- Mar 8, 2022
- Open Bids
- Apr 8, 2022
- Take to Board
- Apr 21, 2022
- Date of Commencement and
Ground
Breaking
- May 5, 2022
- Completion
- Jun 30, 2023